Autodesk Navisworks TimeLiner supports a variety of scheduling software.
This data source requires Microsoft Project 2007™ to Microsoft Project 2013™ to be installed.
This data source requires a number of elements to be installed alongside Autodesk Navisworks:
PPM 6 - 8 is database driven, and as such require the Software Development Kit to be installed in order to set up the ODBC data source link. This can be installed and setup from the Project Management CD by taking the following steps:
On connecting to PPM 6 - 8 within TimeLiner, a logon dialog box allows the source link to be selected (a warning occurs if none are present). The user name and password are not stored in the Autodesk Navisworks file, and will be prompted for each time.
Once connected, a dialog box allows the user to select which project to open. A check box determines if all sub-projects are opened.
By default, TimeLiner brings through Start, End, Planned Start, and Planned End as Start, Finish, BL Start and BL Finish respectively.
Other Primavera dates can be selected through the generic Field Selector Dialog Box, including Project Activity Codes, Global Activity Codes, and User Defined Fields.
The TimeLiner hierarchy supports the WBS structure for Project / Activity hierarchy.
TimeLiner can read Microsoft Project™ MPX files directly, without needing a copy of Microsoft Project™ (or any other scheduling software) installed. Primavera SureTrak™, Primavera Project Planner and Asta Power Project™ can all export MPX files.
Accessing the Primavera P6 Web Services capability greatly speeds up the time taken to synchronize TimeLiner and Primavera schedules.
This data source requires you to set up a Primavera Web Server. Refer to the Primavera P6 Web Server Administrator Guide (available in your Primavera documentation).
This data source requires the corresponding version of Asta Power Project™ to be installed.